Building a roundhouse the work continues

Posted by Ian Daniel on 27 May 2010
Giving a hand with the purling
Giving a hand with the purling
Placing the purling above the doorway
Natural fibre cordage covered in tar and used to tie the posts
Dafydd, Tim and Andy fixing higher purlings

We've been working on the purling which will hold the thatch. I'm really interested in how we build the roof. Dafydd, Tim and Andy have even allowed me to help out! I'll be in the Village between Monday and Thursday next week. If you are around call in.

 

Building a roudhouse - the roof

Posted by Ian Daniel on 13 May 2010
Placing the rafters
Placing the rafters
Placing the rafters
Rafters on the floor ready to be placed
A look at the rafters from below
A look at the rafters from below
All the rafters almost in place
All the rafters almost in place

The house is taking shape now it's all quite exciting. You can see how it will eventually look when Dafydd and the team have finished their work.

Dafydd's had plenty to think about though. The first six rafters went up easily but then he had to decide where to place the ring-beam - inside or outside the rafters? As you can see from the pictures he place them outside the rafters. You can find out why in Dafydd's diary.

Once the ring beam was placed the next set of rafters went up quickly. They were notched, allowing them to hook onto the ring-beam and then lashed with tarred string. A second ring-beam was then placed lower down. Before long we will be thatching.

Link to Dafydd's diary http://www.theroundhouse.org/dafsdiary.htm

Building a roundhouse - continued

Posted by Ian Daniel on 5 May 2010
Roof plan
Roof plan
Starting on the rafters
Dafydd Wiliam and the team discussing the position of the rafters
We've used scaffolding to assist us here. I wonder how they did this in the Iron Age?
We've used scaffolding to assist us here. I wonder how they did this in the Iron Age?
The main raffter poles tied at the apex
The main rafter poles tied at the apex

We started on the rafters yesterday. There will be 36 ash rafters in all. We will be creating ring beams and using a load of hazel rods for the purlins and sways. Come over to see the work develop this week.

Thanks to everyone who called in over the bank holiday weekend - it was great fun!